Flow of Activities

Help Save Lives – Donate to Sri Sri University Hospital

October 2020

Construction of 200 bed hospital building started

January 2022

Hospital of 200 bed ready

January 2021- March 2022

Interior and Fittings to be Completed and procurement of Human Resource

January 2022

Startup of 1st Phase Construction of College minimum Six Class Rooms with Anatomy and Physiology Departments and Laboratories and Quarters for Doctors and Paramedic Staffs.

June 2022

Fully Equipped Hospital for Phase 1 with Doctors, Equipments and Human Resource recruitement for College

July 2022

1st Inspection of CCIM for Hospital and College - Phase 1

September 2022

Second and Final Inspection for approval of 1st Academic years of Bachelor of medicine and surgery

September 2022

On base of approvals we go on for Marketing for Bachelor of medicine and surgery Admissions

January 2023- Febuary 2023

1st Batch admission of Bachelor of medicine and surgery